Large Cistern Slab Pour

In light rain on Wednesday morning the cistern slab was poured (26 yards).  This is what is basically the lower level of the house.  It consists of the electrical room and two compartments of the larger 30K+ gallon cistern.  Thursday was spent starting to get the forms for the cistern walls up as well as getting the forms in place for the smaller cistern’s ceiling.

01-05-2011 - Large Cistern Pour

01-05-2011 - Large Cistern Pour

01-05-2011 - Large Cistern Pour

01-05-2011 - Large Cistern Pour

01-05-2011 - Large Cistern Pour

01-05-2011 - Large Cistern Pour

01-06-2011 - Large Cistern Wall Forms

01-06-2011 - Large Cistern Wall Forms

01-06-2011 - Large Cistern Wall Forms

01-06-2011 - Large Cistern Wall Forms

01-06-2011 - Small Cistern Ceiling Form

01-06-2011 - Small Cistern Ceiling Form

01-06-2011 - Small Cistern Ceiling Form

01-06-2011 - Small Cistern Ceiling Form

One of our other inspectors - Guiness

One of our other inspectors - Guiness

Ready to Pour the Big Cistern

The cistern floor is scheduled to be poured in the morning and the small cistern forms have been removed.

12-31-2010 - The Big Cistern and Electrical Room

12-31-2010 - The Big Cistern and Electrical Room

b

01-04-2011 - The Big Cistern and Electrical Room

01-04-2011 - The Big Cistern and Electrical Room

01-03-2011 - The Small Cistern

01-03-2011 - The Small Cistern

St. Croix Construction – This week’s progress

What a pleasant surprise  to see progress this week.  I wasn’t sure what to expect with the week being book-ended by holidays.  After the pour on Monday work began on the forms for the cistern walls.  Digging of the “main” 30K gallon cistern began as well. On Wednesday the cistern wall forms were completed and the main cistern excavation continued. Today the smaller 15K gallon cistern walls were poured (12 yards).

Materials update:
6 tons of re-bar were purchased from San Juan 2 weeks ago.
Prepaid 200 yards (of the estimated 550) of concrete last week.

The First Pour

We had our first delivery of concrete today.  13 total yards in two trucks.

12-27-2010 - Cistern

12-27-2010 - Cistern

12-27-2010 - Cistern Pour

12-27-2010 - Cistern Pour

12-27-2010 - Cistern Pour

12-27-2010 - Cistern Pour

12-27-2010 - Cistern Pour

12-27-2010 - Cistern Pour

Let’s Dig Some Holes – Cistern #1

Today was a good day.  Even though we spent the past three weeks moving dirt, clearing brush, and “mobilizing”, today is the first day we did some real digging.  Progress. I like it.  Then plan is to get the smaller 15,000 gallon cistern poured this week.  Probably not the most ambitious of plans, but I will take it.  After waiting so long to get to this point I am ready for some concrete.

December 20, 2010 - Cistern

December 20, 2010 - Cistern

December 20, 2010 - Cistern

December 20, 2010 - Cistern (Roseway in background)