St. Croix Construction – This week’s progress

What a pleasant surprise  to see progress this week.  I wasn’t sure what to expect with the week being book-ended by holidays.  After the pour on Monday work began on the forms for the cistern walls.  Digging of the “main” 30K gallon cistern began as well. On Wednesday the cistern wall forms were completed and the main cistern excavation continued. Today the smaller 15K gallon cistern walls were poured (12 yards).

Materials update:
6 tons of re-bar were purchased from San Juan 2 weeks ago.
Prepaid 200 yards (of the estimated 550) of concrete last week.

The First Pour

We had our first delivery of concrete today.  13 total yards in two trucks.

12-27-2010 - Cistern

12-27-2010 - Cistern

12-27-2010 - Cistern Pour

12-27-2010 - Cistern Pour

12-27-2010 - Cistern Pour

12-27-2010 - Cistern Pour

12-27-2010 - Cistern Pour

12-27-2010 - Cistern Pour

Let’s Dig Some Holes – Cistern #1

Today was a good day.  Even though we spent the past three weeks moving dirt, clearing brush, and “mobilizing”, today is the first day we did some real digging.  Progress. I like it.  Then plan is to get the smaller 15,000 gallon cistern poured this week.  Probably not the most ambitious of plans, but I will take it.  After waiting so long to get to this point I am ready for some concrete.

December 20, 2010 - Cistern

December 20, 2010 - Cistern

December 20, 2010 - Cistern

December 20, 2010 - Cistern (Roseway in background)

Pre-build Update

A quick update. We have spent the past year and a half working with an architect, getting permits, getting copies of drawings made, getting a mortgage, getting more copies of drawings made, hiring a contractor, and yes, getting even more copies of drawings made. This process took about a year longer than we anticipated. Whenever anybody tells you that things take longer here on St. Croix, believe them. It just does. There is never any rush, and if there is, it is only you doing the rushing.

The four month architecture drawings took eight, not including some modifications. The one month mortgage approval with Scotia Bank took six months. The permits actually were ready in a reasonable two months or so, both DPNR and CZM. Choosing a builder took a few months. Working with the chosen builder to make modifications to get our costs down took another three months. Of course much of this overlapped, but we were at a stand-still for a few months waiting on the mortgage. When we were finally ready to close, the builder wasn’t quite ready, and then we had the wettest October in history. We closed on our mortgage in early November. Nothing much happened in November except that we were now paying excessive building insurance premiums on a vacant lot.

Shortly after closing my builder told me I should look into mowing the lot. My first thought was “aren’t you just going to bulldoze everything?” I purchased a weed-eater and went to work. I worked for four hours and got about 5% of the lot trimmed. So that little project was a failure, but hey, I got a nice new piece of equipment which I will use approximately two more times.

At the beginning of December our builder started to clear the lot with real machinery. Finally, some tangible progress.  Why did I buy that weed-eater?

December 2, 2010

December 4, 2010

December 11, 2010

December 17, 2010